Checking final preparations

Before you begin

DANGER
HEAVY EQUIPMENT: PERSONAL INJURY OR EQUIPMENT DAMAGE MAY RESULT IF MISHANDLED (D006)

Procedure

  1. Verify that the customer has two ac power sources for each rack being installed.
  2. Verify that the customer has ordered, supplied, and routed the following cables to the storage facility being installed.
    Note: Routing of the customer cables must not be billed against the installation. If the customer wants the service representative to route the cables, that activity must be coded or billed separately.
    1. Fibre Channel cables from external systems to the storage facility host adapters.
    2. An Ethernet LAN cable from the customer network to the primary customer network connection for each management console.
      Note: A second customer network connection to each management console can be added by RPQ.
  3. Go to the next section.