The table that follows provides an overview of the sequence of required and optional
tasks to install the Model 983 into a customer provided rack.
There are four cable bundles. Each is specified in Table 1 to assist in understanding the rack
assembly sequence.
Table 1. List of
sections
| Section |
| PREPARING |
| Section-1, List of sections |
| Section-2, Overview |
| Section-3, Two system service representatives are required to install this system |
| Section-4, Unpacking and verifying that the ship group is complete |
| Section-5, Checking the prerequisites on the customer provided rack |
| ASSEMBLING |
| Section-6, Installing the 4U rails for the UPS (E61 and E62) |
| Section-7, Installing the lower UPS (E62) on the 4U Rails |
| Section-8, Installing the upper UPS (E61) on the 4U rails |
| Section-9, Installing the rails for the management enclosure |
| Section-10, Installing the cable management arm support |
| Section-11, Cable bundle 1, Installing the cable management arm, latching front and rear |
| Section-12, Installing the management enclosure on the rails |
| Section-13, Cable bundle 1, connecting to the management enclosure |
| Section-14, Cable bundle 1, separating the cable groups hanging down |
| Section-15, Cable bundle 1, installing the UPS cable tie bar |
| Section-16, Cable bundle 1, connecting green to upper UPS (E61) and yellow to lower UPS (E62) |
| Section-17, Installing the rails for the lower CEC enclosure (XC2) |
| Section-18, Installing the lower CEC enclosure (XC2) on the rails |
| Section-19, Cable bundle 1, installing the lower CEC enclosure (XC2) cable tie bar and connecting cables |
| Section-20, Installing the rails for the upper CEC enclosure (XC1) |
| Section-21, Installing the upper CEC enclosure (XC1) on the rails |
| Section-22, Cable bundle 1, installing the upper CEC enclosure (XC1) cable tie bar and connecting cables |
| Section-23, Installing the rails for the I/O enclosure (IG3/1G4) |
| Section-24, Installing the I/O enclosure (IG3/1G4) on the rails and installing the front bezel |
| Section-25, Installing the rails for the lower flash enclosure (I1-F04) |
| Section-26, Cable bundle 2, Installing the I/O enclosure (1G3/1G4) cable tie bar and connecting cables |
| Section-27, Cable bundle 2, Connecting to the upper CEC enclosure (XC1) |
| Section-28, Cable bundle 2, Connecting to the lower CEC enclosure (XC2) |
| Section-29, Cable bundle 2, connecting green to upper UPS (E61) and yellow to lower UPS (E62) |
| Section-30, Cable Bundle 1, Connecting to I/O enclosure (1G3/1G4) |
| Section-31, Installing the lower flash enclosure (I1-F04) on the rails |
| Section-32, Installing the rails for the upper flash enclosure (I1-F03) |
| Section-33, Installing the upper flash enclosure (I1-F03) on the rails |
| Section-34, Cable bundle 3, installing cable tie bar at upper flash enclosure I1-F03 |
| Section-35, Cable bundle 3, connecting to the lower flash enclosure (I1-F04) |
| Section-36, Cable bundle 3, connecting to the upper flash enclosure (I1-F03) |
| Section-37, Cable bundle 3, connecting to the I/O enclosure (1G3/1G4) |
| Section-38, Cable bundle 3, connecting green to upper UPS (E61) and yellow to lower UPS (E62) |
| Section-39, Cable bundle 4, connecting to the I/O enclosure (I1-G3/G4) (optional feature) |
| Section-40, Cable bundle 4, connecting to the upper CEC enclosure (XC1) (optional feature) |
| Section-41, Cable bundle 4, connecting to the lower CEC enclosure (XC2) (optional feature) |
| Section-42, Installing the FC 1765 keyboard display (optional feature) |
| Section-43, Connecting the keyboard display |
| Section-44, Routing the mainline power cables, not connecting to the UPS |
| Section-45, Storing the service items |
| COMPLETING |
| Section-46, Completing the Model 983 assembly in the rack |
| Section-47, Reference |